Project Extension and Category A Office Refurbishment, Queen Victoria Street, London EC4
Project Team MHBC (Employer's Agent)
SPPARC Architecture Ltd (Architect)
Capita Symonds (Building Services Engineers)
Pell Frishmann (Structural Engineers)
HCD Management Limted (CDM Co-ordinator)
Bouygues UK (Main Contractor)
Keltbray Ltd
Client QVS Trust
Primary Category Fit Out
Category
Commercial Fit Out Education
Public Buildings Historic Buildings Special Projects
Hotels Leisure & Performing Arts Residential

Services Offered
Project Management Quantity Surveying Building Services / Cost Management
Contract Admin Fire Insurance Reinstatement Cost Assesment Litigation Support
Project Monitoring Construction Consultancy Risk Management

Summary Major Category A office refurbishment in the heart of the City of London
Project Detail
Having assisted in numerous feasibility studies for various parties for works to this building at Queen Victoria Street since 2004, Fanshawe were finally appointed as Quantity Surveyor in 2011 for the refurbishment of the building.
The works comprised significant demolition works, a completely new facade to the front elevation and the complete restructuring of the internal areas to improve the use of the space and to maximise the net internal floor area. A further rooftop extension was also incorporated into the scheme to increase the net lettable area by approximately 4,000m², resulting in an overall net lettable area of approximately 17,400m² over 8 levels. The reconfiguration of the cores included new staircases and scenic lifts with a new central core incorporating 6Nr new passenger lifts and toilet facilities. The project included the creation of two new atria to facilitate the entry of natural light into the building. Other elements of the project included an impressive new front reception, a smaller rear reception, car parking facilities, a bicycle store and associated shower / changing facilities and a green roof. The net office areas included typical Category A installations including new raised floors and suspended ceilings and new services (new four pipe fan coil units and new lighting).
The project comprised two separate Contracts - a Strip Out Contract (carried out under the JCT Intermediate Building Contract) and a Main Contract (carried out under the JCT Standard Building Contract Without Quantites). The Strip Out Contract was completed over a period of 15 weeks with the Main Contract commencing in September 2012. 
Works were completed in August 2013 culminating in a complete transformation of the building.

 


Value £33 million (Construction Cost)
Show Value Yes
Completion July 2014
Main Image  Download me! Main Picture.jpg Download
Image 1  Download me! Picture 1.jpg Download
Image 2  Download me! Picture 2.jpg Download
Image 3  Download me! Picture 3.jpg Download
Download
Date Posted 31 Jul 2014
Archive Date 31 Jul 2024