Show on Website Yes
Show on Homepage Yes
Project Category A and B Fit Out at 1 Canada Square
Project Team Savills Commercial Limited (Employer's Agent) Pringle Brandon Perkins + Will (Architect) WSP Group (Building Services Engineers) Shore Engineering Limited (CDM Co-ordinator) BW Interiors (Main Contractor)
Client MDU Services Limited
Primary Category Fit Out
Category
Commercial Fit Out Education
Public Buildings Historic Buildings Special Projects
Hotels Leisure & Performing Arts Residential

Services Offered
Project Management Quantity Surveying Building Services / Cost Management
Contract Admin Fire Insurance Reinstatement Cost Assesment Litigation Support
Project Monitoring Construction Consultancy Risk Management

Summary High quality Category A and B fit out at 1 Canada Square in Canary Wharf
Project Detail
Fanshawe were the Quantity Surveyors on this fit out for MDU Services Limited at 1 Canada Square, the well-known skyscraper in Canary Wharf that was the tallest builidng in London for approximately 20 years.  The Contract Works comprised a fit out to Category B from shell and core incorporating the lobbies and WCs.
The Category A and B fit out provided approximately 47,000 sq ft of office accommodation spread over two floors.  Category A Works only were also carried out to a further 9,000 sq ft for occupation by a separate tenant at a later date (including a new demise wall), together with works to core areas.
The fit out comprised largely open plan office areas with typical office facilities (cellular offices, informal and formal meeting rooms, training rooms, tea points, copy points, Comms Rooms, an AV Room, additional toilets and shower facilites.  One of the floors incorporated the main reception and the Client's formal meeting rooms.
As part of the works the Contractor carried out the replacement of the on-floor central plant and also fitted out the toilet areas and lift lobbies.
The Main Contractor completed the project in an overall programme of 19 weeks under the JCT Design and Build Contract.  This included Sectional Completion for part of the works allowing early completion of the Client's Comms Room, AV Room and the separate Category A demise on one floor.
Works were completed on time and within MDU's budget.

Value Confidential
Show Value Yes
Completion November 2014
Main Image  Download me! Main Picture.jpg Download
Image 1  Download me! Picture 1.jpg Download
Image 2  Download me! Picture 2.jpg Download
Image 3  Download me! Picture 3.jpg Download
Download
Date Posted 01 Dec 2014
Archive Date 01 Dec 2024
Creation Date 23 Feb 2015
Modification Date 24 Feb 2015

Back to Projects

URL:  http://www.fanshawe.co.uk/metadot/index.pl?iid=2802
Printed on:  December 14, 2018 8:03 PM